
Draft Evaluation of the
Florida High Speed Rail Project
January 1998
Draft Ridership Study
Prepared by
Wendell Cox
Wendell Cox Consultancy
for the
James Madison Institute
March 1998
Abstract
The Florida Department of Transportation and Florida Overland Express intend to build and
operate a high speed rail line between Miami, Orlando and Tampa. Last year, the James Madison
Institute published research indicating that the high speed rail line was likely to produce a
substantial deficit, which would be the responsibility of Florida taxpayers. Recently, FDOT's
ridership projections were increased by 28 percent. This report uses eight independent tests to
evaluate the new ridership projections and finds that under each, a substantial deficit would
occur. Two comprehensive tests are used to estimate the overall deficit from not only ridership,
but also higher costs, which conclude that the eventual deficit could cost Florida taxpayers from
$11 billion to $37 billion more than planned.
Executive Summary
A 1997 report by the James Madison Institute concluded that the proposed Miami-Orlando-Tampa high speed rail line would carry many fewer passengers than projected, cost much more
than projected and expose the taxpayers of the state to enormous financial exposure. New
ridership projections were provided in January 1998. The new 2010 ridership projection is up
nearly 30 percent from the original FOX projection, while overall fare revenues are projected to
be seven percent higher. Fare revenues were projected to rise at a lower rate than ridership
because a lower average high speed rail fare was assumed.
Florida taxpayers would pay for deficits created by unreliable forecasts: Accurate ridership
projections are crucial to the success of this project. In the final analysis, the taxpayers of Florida
will take the entire risk for both over projection of revenues as well as under projection of capital
and operating costs. The high speed rail developers will be liable only to the extent of their
investment (less than 5 percent of project capital and debt service cost). Private bondholders will
be protected by a state guaranteed "covenant to complete and operate," which will have the same
effect as the full faith and credit of the state of Florida.
New ridership forecasts appear to be unreliably high: Considered in the light of recent market
and research developments, the new ridership and revenue projections appear to be high and are
likely to translate into substantial additional subsidy obligations for Florida taxpayers. Eight
independent sensitivity analyses (tests) are presented. Each of the deficit amounts estimated
assumes that the project would be built and operated within current cost projections. That is
considered highly unlikely (see "Comprehensive Tests" below).
The USDOT Federal Railroad Administration forecasts are considerably lower than
the new forecasts: Revenue projections by the Federal Railroad Administration (FRA)
for virtually the same route are at least 35 percent lower than the new projections. This
could require $6.5 billion to $8.5 billion in additional Florida taxpayer subsidies.
2. Proposed high speed rail fares will need to be reduced to compete with air fares: To
compete for airline passengers, high speed rail will need to charge fares that are no higher
than air fares. Currently air fares are 20 percent lower than projected high speed rail fares,
and could fall to at least 32 percent below in response to high speed rail competition.
Lowering fares to equal air fares would require $3.5 billion to $6 billion in additional
taxpayer subsidies.
The higher airline passenger attraction is inconsistent with falling air fares: Since
the original FOX projection, air fares have fallen 52 percent relative to proposed high
speed rail fares. According to an FRA formula, this should have resulted in a reduction of
16 percent to 39 percent in high speed rail ridership, instead of a 28 percent increase. This
discrepancy could produce an additional deficit of $3 billion to $7.5 billion to be paid by
Florida taxpayers.
4. The new projections assume an unreasonably high attraction of airline passengers:
At the more realistic air passenger attraction rate estimated by FRA, the Florida high
speed rail project would sustain a $7 billion higher deficit, which would be the
responsibility of Florida's taxpayers.
The connecting passenger airline market potential appears to be nil. The new
projections supplied by French National Railways consulting unit, Systra, assume that
nearly 1.5 million annual connecting ("air connect") passengers will be supplied by
airlines operating in Florida markets. Systra assumes that airlines could reduce operating
losses by using high speed rail for connecting passengers, instead of short distance airline
flights. But it appears that airlines are earning profits on short distance flights. There does
not appear to be any compelling reason for any airline to outsource its short distance
Florida passengers to FOX. Further, Systra appears to overestimate the size of the air
connect market. There seems to be no realistic potential for high speed rail to attract any
of the "air connect" market, which would reduce high speed rail revenues by $7 billion,
which would have to be made up by Florida taxpayers.
6. The short distance projections are unreasonably high: The new projections continue
to assume unreasonably high ridership in the short distance markets in which high speed
transportation (airlines and high speed rail) is incapable of competing with door to door
automobile travel times (the Tampa to Orlando and Palm Beach to Miami corridors). This
over-projection is likely to produce a deficit of $1.5 billion, which will be the
responsibility of Florida taxpayers.
A higher service level is assumed, which increases costs: The new projections assume
a 15 percent higher level of service, which will increase operating costs $1.5 billion.
8. Europe: Lower ridership and higher costs: The two London-Paris-Brussels high speed
rail lines are on the brink of commercial collapse. There is a very real possibility that the
private developers will either withdraw or have their franchise relinquished. Ridership
projections for the two lines is only 10 percent higher than the new Florida projections
for a single line, despite a market three times as large as the Florida market. Further, there
are indications that new high speed rail lines in Europe will be poorly patronized and
sustain heavy losses.
There are no consulting firms that have a record of success in projecting US high speed rail
ridership: Despite claims of previous accuracy by the two consulting firms that produced the
projections, the new projections contain significant inconsistencies compared to their own
previous projections. There are also significant inconsistencies between the projections of the
two firms. Moreover, no consulting firm can claim to have accurately projected high speed rail
ridership in a nation that has near-market petroleum prices and a vibrant competitive airline
industry, because that exists only the United States, where no high speed rail has ever operated.
Comprehensive tests show substantial deficits: Two sensitivity analyses are presented that
take into consideration the ridership, revenue, operating cost, capital cost and debt service with
respect to the proposed Florida high speed rail line.
National Research Council: Transportation Infrastructure Projections are Often
Incorrect: A recent study published by the National Research Council notes that large
transportation infrastructure costs are commonly 50 to 100 percent above projections,
while usage (ridership) can be 20 to 60 percent lower than projections. If these figures are
applied to the Florida high speed rail project, additional taxpayer financed subsidies of
$11 billion to $31 billion could be required. The inaccuracy of such forecasts has led
noted economist Charles A. Lave to propose that consulting firms be required to bond the
accuracy of their projections.
James Madison Institute: Substantial Deficits Projected for FOX: The 1997 JMI
Evaluation projected that under the most favorable conditions, the Florida high speed rail
line would carry 55 percent fewer riders than forecast, generate 45 percent less revenue,
with 15 percent higher capital costs and 29 percent higher operating costs. At these rates --- all below or within the range suggested by the National Academy of Sciences research,
Florida taxpayers would be required to pay an additional $11 billion in subsidies. In the
worst case, additional taxpayer subsidies of more than $37 billion could be required --- a
range similar to that suggested by application of the National Academy of Sciences
research findings.
The tab for Florida taxpayers: $11 billion to $37 billion more: These comprehensive tests
suggest that Florida taxpayers could be required to provide from $11 billion to $37 billion in
additional subsidies to high speed rail. Once the bonds are issued, the taxpayers will have little or
no financial control, because of the state's covenant to complete and operate the high speed rail
system.
1. Introduction
A high speed rail line has been proposed for the Miami-Orlando-Tampa corridor. Trains would
operate at up to 200 miles per hour. The Florida Department of Transportation (FDOT) and the
developer, Florida Overland Express (FOX) believe that the line will attract significant numbers
of travelers from automobiles and airplanes. The state of Florida would provide $3 billion in
subsidies, the federal government $300 million, Orlando International Airport $100 million and
Miami International Airport $50 million. FOX would provide $350 million in equity, construct
the line, build the trains and operate the system for 40 years. Infrastructure debt of $6.5 billion
would be required (1995$).(1)
The James Madison Institute published a detailed analysis of the high speed rail project in April
1997, Evaluation of the FDOT-FOX Miami-Orlando-Tampa High-Speed Rail Proposal (JMI
Evaluation).(2) This analysis was based upon FDOT, FOX, generally available planning and
market data and high speed rail experience around the world. The JMI Evaluation found that
high speed rail is likely to cost much more than projected, carry many fewer passengers than
projected and expose the taxpayers of the state to enormous financial exposure.
Recently FDOT and FOX have published a new ridership study,(3) which projects 28 percent more
ridership than the original FOX proposal, at 8,256,000 for the year 2010. This new projection is
the mid point of two separate projections by Systra, the "consulting arm"(4) of the French
Railways, SNCF,(5) (8,504,000) and KPMG Peat Marwick (8,008,000).(6)
While the ridership projection has risen, the projected average fare per trip has been reduced by
nearly 17 percent from the original FOX proposal (though costs per trip remain higher than
automobile and airlines).(7) Annual fare income is thus approximately seven percent
(approximately $30 million annually) above the level in the original FOX proposal.(8)
This report applies eight independent tests to the new ridership projection and provides
sensitivity analyses estimating financial implications. The report also applies two comprehensive
tests to the ridership and cost projections, including the findings of National Research Council
research on the experience in forecasting the performance of transportation infrastructure projects
and the JMI Evaluation findings.
2. Why the Ridership Forecast is so Important
The "down-side" accuracy of ridership forecasts is crucial to the financial viability of the Florida
high speed rail project. If ridership is lower than projected, revenues will also be lower and the
result will be a larger capital and operating deficit, and a bailout of project bonded indebtedness
could be required.
In this project, the private developers (FOX) risk only their capital --- a substantial amount, but
very small in relation to project costs and the potential for a larger deficit. Moreover, FOX profits
are paid before debt service payments are made. Promoters have claimed that the state will be
provided with a "fixed price" under the contract with the developers. A fixed price contract,
however, will provide the state no guarantees, since the private developers will not (and probably
could not) supply financial guarantees to bond against capital cost, operating cost and subsidy
increases. The FOX partners will limit their legal liability to the extent of their investment, which
is less than five percent of the project cost. As would be the case with any rational business
organization, FOX cannot be expected to shoulder the substantial losses that could arise from
what have become typical capital and operating cost overruns, or substantial shortfalls in fare
revenue arising out of ridership forecasts that were too high.
The project will be financed with Florida tax revenues and bonded indebtedness.(9) FDOT and
FOX are seeking federal guarantees for all or part of the bonded indebtedness. The bond holders,
however, do not represent a resource for bailing out the project if revenue projections are not
reached. Like FOX, the bondholders will have no risk. To make the bonds marketable will
require that the state of Florida covenant to complete and operate the project. This represents a
"de facto" pledge of the full faith and credit of the state of Florida. This leaves the risk for
financial failure to the taxpayers of Florida.
The risk is genuine. Each one percent reduction in fare revenue translates into a nearly
$200 million bill for state taxpayers.(10) Each one percent increase in costs translates into
more than $150 million in additional taxpayer subsidies. The record with respect to large
infrastructure projects suggests that the Florida high speed rail ridership and cost
projections will prove to be considerably less accurate (see "Unreliable Projections").
The financial risk is substantial. If, for example, revenue falls 20 percent short of
forecast, revenues would be insufficient to fund the bonded indebtedness and Florida
taxpayers would be required to bail the project out financially. Similarly, a 15 percent
increase in projected costs would also leave the project unable to service its debt --- even
if the ridership and revenue projections were met. The financial status of the project is
tenuous. The project's success depends upon closely achieving the ridership, revenue and
cost projections.
The risk of failure could be imminent. As was indicated in the 1998 JMI Evaluation,
project revenues could be insufficient to service bonded indebtedness within five years
(see "Developments in Europe: Losses and Higher Subsidies").
3: Independent Tests
A series of independent tests (sensitivity analyses) were applied to the new ridership and revenue
projections. These tests assume that capital and operating expenses will be at the projected level --- an assumption considered highly unlikely (see "Comprehensive Tests" below).).
3.1: The New Projection: Higher than USDOT FRA Projection
The new ridership and revenue projections are much more optimistic than projections developed
for the US Department of Transportation Federal Railroad Administration (FRA)(11) over virtually
the same route. The Tampa-Orlando-Miami corridor was included in a review of 10 high speed
rail corridors, none of which were projected to be profitable by 2020. FRA projected the 2020
Florida high speed rail revenue would be 45 percent lower than the original FOX projections.
| At FRA projected high speed rail revenues the Florida high speed rail project could require $9 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).).) |
3.2: The Projected Rail Fares are Higher than Airfares
More than 30 percent of the Systra-KPMG projected high speed rail ridership is expected to be
diverted from the airlines.(12) Attraction of air travelers will require, among other things, high
speed rail fares that are competitive with (no higher than) air fares. Average air fares are now
nearly 20 percent below high speed rail fares.(13) The present air fare structure is not indicative of
the ability of airlines to compete on price. At their lowest point in the last two years, Florida air
fares were 32 percent below the new lower rail fares.
| At rail fares competitive with airline fares, the Florida high speed rail project could require $3.5 billion to $6 billion in additional Florida taxpayer subsidies.(14) |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |
3.3: Ridership is Up Despite Significant Air Fare Drop
The new projections are questionable in light of the downward trend in air fares.
At the time of the original projections, FOX assumed that airfares would be
approximately 65 percent above the projected high speed rail fares. Air fares are now 20
percent below projected high speed rail fares.
In an analysis of the Florida market, FRA estimated that a 30 percent reduction in air
fares would translate into a 10 to 24 percent reduction in high speed rail ridership.(15) Air
fares have dropped 52 percent relative to the high speed rail fares as originally projected
by FOX. At the FRA rate, this would translate into a reduction of 16 to 39 percent in
diversion of airline passengers --- 300,000 to 800,000 passengers.
Instead, however, the new projections indicate an increase of 28 percent in high speed rail
ridership (Chart: Relationship: Change in Air Fares & High Speed Rail Ridership). At least one
of the two projections is faulty. In view of the inordinately high airline market share projected by
Systra-KPMG and the unsupportable air connect passenger projection (below), the earlier
projection would appear to be the least incorrect. (The JMI Evaluation projected the original
FOX projections to be nearly 100 percent high.)
| If rail ridership were to respond to lower airfares at FRA projected rates, the Florida high speed rail project could require $3 billion to $7.5 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |

3.4: The Projected Air Passenger Attraction is Unreasonably High
The new ridership projections assume that the high speed rail line will attract 58 percent(16) of the
airline market. This figure appears to be well beyond the range of probability.
FRA projected a 21 percent high speed rail airline market share for virtually the same
route. None of the 10 high speed rail corridors studied by FRA achieved ridership
approaching the 58 percent FOX projection.
High speed rail has attracted only 30 percent of the air market in the London to Paris
corridor, and 17 percent in the London to Brussels corridor.(17)
In the Washington-New York corridor, where Amtrak's near high speed rail trains offer
point to point time savings relative to airline service, rail achieves only a 40 percent of
the combined air-rail market share, despite first class rail fares that are at least one-third
less costly than airline coach fares and more spacious and comfortable accommodations.(18)
The airline business is fluid and competitive. Airlines will respond to competition by FOX in the
same manner that they have responded to airlines that charge lower fares --- by lowering fares. It
is reasonable to assume that FOX would attract no more than 20 percent of airline passengers.
| At FRA projected air passenger attraction rates, the Florida high speed rail project could require $4 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |
3.5: The Air-Connect Market Potential Appears to be Nil
Perhaps the weakest element of the new projections is the finding that high speed rail would
become a subcontractor to the airlines for providing service in Florida markets. This "air
connect" market segment would constitute more than 15 percent of FOX ridership. This
proposition is based upon three assumptions that are likely to be faulty:
That the airlines are losing money on shorter flights.(19)
That it is in the interest of the airlines to outsource service to FOX.
That the number of "air-connect" passengers on two airlines is sufficient to generate 1.5
million annual FOX riders.
In its only serious criticism of the Systra-KPMG reports, the "peer group" expressed concern
about the size of the "air connect" attraction assumption.(20) It is notable that FOX has provided no
expressions of interest from either of the two potential partners, American Airlines and Delta
Airlines.
The air connect market as described: Most of the ridership attracted from airlines is projected
to be "air connect" passengers (connecting passengers). Air connect passengers begin or end their
trips outside the high speed rail corridor. For example:
A domestic air connect passenger could be traveling from Indianapolis to Miami, with an
intermediate stop and usually a plane change in Orlando.
An international air connect passenger could be traveling from Rio de Janeiro to Orlando,
with an intermediate stop and perhaps a plane change in Miami.
Systra assumes that FOX would establish a "code share" arrangement with a hub airline in Miami
and a hub airline in Orlando. A code share arrangement involves the use of smaller regional
airlines to provide service under the larger carrier's name and logo in corridors that have
insufficient demand or are too short to operate full sized airline jet equipment. Many airlines
have "code share" arrangements with smaller airlines to provide services from hub airports to
airports to which demand is too low or the distance is too short for the airline to cost effectively
employ its jet fleet.
Systra indicates that in 1997 1.7 million air connect passengers traveled in the high speed rail
corridor.(21) By 2010, Systra projects the air connect market to grow to 2.7 million annual
passengers. Approximately 55 percent of air connect passengers are projected by Systra to
transfer to high speed rail.
Short distances flights do not necessarily lose money: Systra claims that the two hub airlines
could achieve "huge cost savings by transferring their local connecting passengers to the rail
mode." However, short distance flights appear to be profitable, and it is unclear how the airlines
would achieve "huge cost savings" by using FOX. For example, Comair, the Delta code share
operator in the Orlando to Miami and Orlando to Fort Lauderdale markets earned a profit margin
more than double that of Delta Airlines in 1996, and ten times that of American Airlines.(22) It
seems unlikely that the stockholders of either Delta Airlines or American Airlines would permit
those carriers to make such substantial investments in their own regional airline subsidiaries, if
they produced losses. Southwest Airlines' aggressive entry into Orlando and Tampa to Southeast
Florida markets would not be rational if profits were not anticipated.
If the airlines were losing money on code share flights, the problem could be immediately solved
by discontinuing regional services. Since deregulation, US airlines have had the authority to
discontinue unprofitable routes whenever they deem appropriate and they have done so. For
example, American Airlines has closed entire hubs in Raleigh-Durham, San Jose and Nashville
due to unprofitability.(23)
Systra indicates that the cost of operating smaller aircraft is likely to increase in the future. It is
not clear why this should be given the fact that airline unit costs have been falling in inflation
adjusted terms.(24) It is expected that short distance airline flights will become more cost effective
in the years to come. Much more efficient smaller, "regional" jets are being purchased by many
airlines and assigned to shorter routes.(25) Some are already being operated in Florida markets, and
many more will be in the future. This means that code sharing with FOX could be less attractive
to the airlines in the future. Moreover, as airline and airspace capacities are increased, lower fare
airlines such as Southwest Airlines, could begin to serve more airports, such as Miami and West
Palm Beach.(26)
The size of the potential air connect market has been over-estimated: This can be illustrated
by an analysis of the present air connect market.
Systra indicates that 954,000 annual air connect passengers traveled in the Central Florida
to Southeast Florida market in 1997 (Orlando to Miami and Orlando to Fort Lauderdale).
One airline has a hub in Miami --- American Airlines, and there is one hub airline in
Orlando that provides service between Orlando and the Southeast Florida market (Delta
Airlines).
If all of the seats in every American Airlines and Delta Airlines code share flights in the
Central Florida - Southeast Florida market were filled with air connect passengers, there
could be no more than 700,000 air connect passengers.
It is estimated that the American Airlines code share flights carry approximately 200,000
annual air connect passengers and that the Delta Airlines code share flights carry
approximately 150,000 annual air connect passengers.(27)
If FOX were able to successfully execute code share agreements with American Airlines and
Delta Airlines, it is estimated that approximately 560,000 annual air connect passengers would
be carried in 2010 by FOX in the Central Florida - Southeast Florida market --- 480,000 fewer
(40 percent less) than Systra projects.
Airlines have no reason to "code-share" with FOX: Systra assumes that FOX will execute
code sharing arrangements with airlines only at Orlando and Miami hubs,(28) and further indicates
that FOX "can attract a large portion of these (air connect) passengers only by having an
agreement with the airlines companies." It is unlikely that any such agreements will be executed.
Under the FOX assumptions, airlines would outsource (contract) service to air connect
passengers to FOX. But much of the code-sharing service in Florida is not out-sourced. It
is provided by the airlines themselves through wholly owned subsidiaries. All American
Airlines code-share service is provided by its "American Eagle" subsidiaries, while some
Delta Airlines code-share service is provided by its "Delta Express" subsidiary. With the
airlines having determined that it is not in their interest to outsource shorter flights to
smaller regional airlines, it seems unlikely that they would outsource the same service to
a high speed rail operator (FOX).
Cost reduction does not appear to be the driving consideration in airline management
decisions on code sharing
arrangements. For example, an
argument could be made that in the
Miami - Orlando market, American
Airlines and Delta Airlines could
reduce costs by combining their code
sharing flights, operating larger, more
cost effective aircraft. They avoid this
arrangement not only in Florida
markets, but in virtually all other
markets. In some shorter distance
markets, luxury bus service could be
used to reduce costs relative to
smaller airplanes, while not seriously
retarding travel times. Yet there are no
significant bus code-share
arrangements among the major
airlines.
There are practical problems with
combining the code sharing flights of different airlines. Currently, code share flights are
scheduled to meet the incoming and outgoing "banks" of flights at hub airports. Use of
high speed rail as a code share provider could make this problem worse. Passengers
would be inconvenienced by longer walks between gates, a second security clearance,
potentially longer connection times and longer travel times. This would probably be
unacceptable to airline marketing managers.(29)
Airlines do not share code sharing flights as a matter of marketing practice. Each hub
airline with code share arrangements requires that its logo and not that of any competitor
appear on all aircraft. From a marketing perspective, it is unlikely that both American
Airlines and Delta Airlines would have a code sharing arrangement with FOX under
which the logos of both airlines would appear on rail cars.
According to Systra, 45 percent of air passengers are local passengers who travel within
Florida markets, rather than air connect passengers. FOX proposes that the airlines would
cancel flights and route its air connect passengers instead by high speed rail. Cancellation
of these flights would leave local air passengers without service. It seems highly unlikely
that the airlines would abandon their local passenger market.
It would therefore appear that the most likely scenario is that FOX would have no code sharing
arrangements with airlines. FOX has provided no evidence that either American Airlines or Delta
Airlines intends to cancel their own services and instead transfer their own passengers to high
speed rail.
| Without the projected air connect passengers, the Florida high speed rail project could require $7 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |
3.6: Short Distance Ridership is Still Grossly Over-Estimated
Originally, FOX projected more than 1.7 million annual passengers would be attracted from the
Interstate 4 corridor between Tampa and Orlando --- more than five percent of the automobile
market. The JMI Evaluation considered this figure exceedingly high because high speed travel
modes are comparatively uncompetitive in time and cost in corridors under 100 miles.(30)
In a short corridor, an automobile averaging 45 to 60 miles per hour can provide a faster door to
door trip than an airplane capable of 600 miles per hour or a train capable of 200 miles per hour.
If Tampa-Orlando were a lucrative high speed market, significant numbers of people would be
using airlines today --- but they are not. Systra projects that high speed rail would attract 100
times as many automobile trips in the Tampa-Orlando corridor as there are local air trips today.
The new projections are lower for the Tampa-Orlando corridor. The reduction, however, is
canceled by a new higher projection for the Miami-Palm Beach corridor. It is estimated that the
short distance ridership projection could be 1,500 percent high.(31)
| At a short distance ridership level consistent with US Department of Transportation data, the florida high speed rail project could require $1.5 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |
3.7: Higher Service Frequencies are Assumed
The new projections are based upon service frequencies that are approximately 20 percent higher
than was originally proposed by FOX.(32) For example, the original FOX proposal anticipated 25
trains per day in each direction between Orlando and Miami. The new Systra projections
anticipate an average of 32 trains daily in each direction between Orlando and Miami. This
additional train service will increase operating costs and could increase infrastructure costs.
| At the higher service levels now proposed, the Florida high speed rail project could require $1.5 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |
3.8: Developments in Europe: Losses and Higher Subsidies
There are already early indications in Europe of the type of financial difficulties the JMI
Evaluation has predicted for the Florida high speed rail project.
A consortium of private developers were selected in 1996 by the British government to operate
high speed rail service from London to Paris and Brussels (Eurostar service) and to build a high
speed link from the Channel Tunnel to St. Pancras Station in London. Ridership, at six million
annually, is running well behind the original SNCF (French National Railways --- parent of
Systra) projections of 15 million and a revised projection of nine million. The Systra report
attributes the failure to reach the nine million ridership projection to service interruptions in the
Channel Tunnel. In the latest year, revenue was 40 percent below projections, and a loss of $240
million was sustained --- larger than its gross revenues of $220 million.(33) However, even if the
nine million ridership projection had been reached, the service would have remained below
revenue projections. It is now projected that the project will sustain losses of $5 billion over the
next 50 years.(34)
In January with capital costs rising 20 percent above projections made only two years before, the
consortium approached the government to seek nearly $2 billion more in subsidies to complete
the project. Their request was denied and the private developers have been given until the end of
March to propose financing alternatives for the project. If such arrangements cannot be made, the
private developers will relinquish their franchise. This is not a negative reflection on the private
developers --- they have a fiduciary responsibility to their stockholders to abandon any endeavor
that looks likely to produce intolerable losses.
There is, however, an important difference between the Channel Tunnel link and the Florida
High Speed Rail project. In Britain, without the artificial market mechanisms of public bond or
financial guarantees, the project could be abandoned even before construction begins. In contrast,
the de facto full faith and credit of the state of Florida could permit that project to proceed to
construction, with state officials being called upon to provide additional subsidies as costs
escalate during the construction process. This has occurred in other recent large infrastructure
projects, such as Denver International Airport, the Channel Tunnel itself, and the Boston Central
Artery. Indeed, these projects tended to escalate in cost by approximately $1 billion annually
during construction --- a figure nearly matched even before construction started in the case of the
Channel Tunnel link. In the United Kingdom, the risk for cost overruns belongs to the developer.
In Florida, the risk for cost overruns belongs to the taxpayers.
Further, the London-Paris-Brussels market is considerably larger than the Miami-Orlando-Tampa
market. The Florida high speed rail project would be a single line serving a population of 8.4
million. The London-Paris-Brussels market has a population of nearly 25 million and is served
by two high speed rail lines (London to Paris and London to Brussels). High speed rail has a
considerable cost advantage over automobiles partly because of costly ferry and Channel Tunnel
shuttle fares. High speed rail also has a greater travel time advantage over the automobile
because of the time necessary to transition from freeways to Channel Tunnel shuttles. Yet the
revised annual projection of nine million annual riders for the two London-Paris-Brussels lines is
little more than the new 8.3 million annual projection for a single line in the Florida market
barely a third the size.
But the problems with high speed rail costs and ridership are even broader. French government
railway official Claude Martinand is reported to have told a recent Paris transportation seminar
that "with few exceptions, France's and Europe's high-speed rail projects would have very low
passenger volumes and he predicted that one of the much-touted EU priority projects - the
Paris-Brussels-Amsterdam-Cologne TGV (high speed rail) link - will be a financial disaster
because the level of users will never pay back the ... cost of building it, nor the ongoing costs of
running it."(35)
| At ridership proportionate to the market size and ridership on the London-Paris-Brussels services, the Florida high speed rail project could require $12 billion in additional Florida taxpayer subsidies. |
| The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. |
3.9: Summary of Independent Tests
The eight independent tests project deficits ranging from $1.5 billion to $12.5 (the average is
$5.5 billion).
|
Independent Sensitivity Analyses Comparison: Additional Florida Taxpayer Subsidies | ||
| Test | Low | High |
| #1: Ridership at FRA Projection | $9.0 Billion | |
| #2: Rail Fares Competitive with Air | $3.5 Billion | $6.0 Billion |
| #3: Riders Lost Due to Lower Air Fares | $3 Billion | $7.5 Billion |
| #4: Airline Rider Attraction at FRA Rate | $4.0 Billion | |
| #5: No "Air Connect" Riders | $7.0 Billion | |
| #6: Reasonable Short Distance Ridership | $1.5 Billion | |
| #7: Higher Service Levels | $1.5 Billion | |
| #8: London-Paris-Brussels Rates | $12.0 Billion | |
| Average | $5.5 Billion | |
| In 1997$ rounded to nearest half billion.
The purpose of the independent sensitivity analyses is to estimate the financial impact of independent ridership tests. It is presumed that capital and operating costs will be no higher than projected. This is considered highly unlikely (see "Comprehensive Tests" below).. | ||
The comprehensive tests described later result in much higher additional Florida taxpayer
obligations, because they take into consideration the operating and capital cost overruns that are
probable as the project proceeds.
4: Unreliable Projections
There are also problems with the projection process itself.
The projecting firms: no relevant US experience: In relation to the FDOT financed ridership
study, both Systra/SNCF and KPMG provide detailed information on the accuracy of their
projections in previous projects.
Systra points to projection successes with respect to high speed rail lines in France and the
Channel Tunnel link. As was noted above, Channel Tunnel high speed rail ridership is running
well below the original forecasts (6 million annual riders compared to the 15 million annual rider
projection).
The French experience is simply not transferable to the United States.
The cost of driving is much more than high speed rail fares in France. Exorbitant taxes
raise the price of gasoline in France to $4.50, approximately four times that in the US.
Intercity freeways are subject to excessively high tolls.
The French government has required air fares on competing routes to be higher than high
speed rail fares, to encourage rail ridership.(36)
France's artificial market manipulations have advantaged high speed rail compared to the
automobile and airlines. High speed rail will not be the recipient of such preference in the US. In
contrast to France, the US is characterized by much nearer market gasoline prices and the cost of
driving will be lower than high speed rail fares. The US, unlike France, has a mature,
competitive, deregulated air market, in which carriers have established their own fares, without
government interference, for nearly two decades. The market price of air fares in Florida markets
is lower, not higher than proposed high speed rail fares. In short, Systra has no experience that
would demonstrate its projection accuracy or inaccuracy with respect to high speed rail in the
much less regulated US market --- because no high speed rail line has been built in the US. The
French experience is simply irrelevant to the much different US market conditions.(37)
KPMG cites a projection success with respect to near high speed rail service in the US northeast
corridor --- the Northeast Corridor Improvement Project. This assignment did not involve
projecting ridership on a new route that was to be built. It was rather a projection of ridership
after improvements were made to an existing route --- a considerably less risky undertaking.
No consulting firm has a history of successful high speed rail ridership projections in the US or
any similar market, because high speed
rail has not been built in such a market.
Any such forecasts must therefore be
highly speculative and subject to
significant error.
Forecasting Discrepancies between
Firms: There are considerable
discrepancies between the new Systra
and KPMG projections.
KPMG projects 500,000 more
passenger diversions from the
automobile than Systra.
Systra projects more than 100
percent more induced ridership
(riders not diverted from airlines
or automobiles) than KPMG.
Forecasting Discrepancies within Firms: There are substantial discrepancies between the
ridership projections of each consulting firm.
Systra now projects annual ridership at 2 million more than its original 1995 FOX projection --- an increase of 32 percent (Chart: Comparison: 1995 & 1997 Projections).
KPMG projects annual ridership at 2.5 million more than its 1995 projection on the FOX
proposal prepared for FDOT --- an increase of 45 percent (Chart: Comparison: 1995 &
1997 Projections).
Systra estimates the number of short distance riders between Southeast Florida and Palm
Beach at 250 percent higher than its own original FOX projection.
Neither firm provides a detailed explanation of the differences between these projections. It is
clear, however, that if high speed rail is built in Florida, each firm will have produced at least
one set of incorrect projections.
Forecasting: An Inexact Science: There are valid reasons why ridership and revenue
projections are often high and cost projections are low. The planners and administrators who
oversaw each of the projects above can supply a litany of reasons why forecasts were not met.
Unforeseen circumstances, such as additional environmental mitigation requirements, changes to
project scope and construction delays can add to costs. Usage projections can be high because
projected demographic trends or market conditions do not materialize. But there are additional
reasons for the unreliability of forecasts. Infrastructure decisions are often made without regard
to the historic inaccuracy of forecasts. Forecasts can also be influenced by political factors.
... forecasts that underscore a priority which is out of political favor are likely to be
ignored, whereas forecasts that support politically favorable positions are likely to be
embraced.(38)
Major infrastructure projects can take on a "life of their own." The experience demonstrates that,
once authorized, even cost escalation that double or triples the cost of a project will not result in
its cancellation. There will always be detailed explanations for cost escalation and failure to
attract projected ridership and revenue --- some are more valid than others. But with regard to
subsidized projects, the effect is the same --- the excess cost is paid by the taxpayers.
It is not unusual for different ridership modeling approaches to produce different results. It is
simply an indication of the volatility --- and possible inaccuracy --- of ridership projections. It is
simply not known which of the projections is most correct or whether any of the projections
would be remotely close to the actual ridership that would be carried.
4: Comprehensive Tests
Two sensitivity analyses are presented that take into consideration the comprehensive impact of
all factors (ridership, revenue, operating cost, capital cost and debt service) with respect to the
proposed Florida high speed rail line.
4.1 National Research Council Study
The potential inaccuracy of projections is not limited to ridership. The JMI Evaluation
summarized the experience with recent large Florida, U.S. and international transportation
infrastructure projects, demonstrating that usage and cost projections have been very inaccurate,
which has translated into higher user and taxpayer costs.(39)
This finding has been repeated in a recent international study published by the National Research
Council's Transportation Research Board, which is perhaps the most highly respected
professional transportation organization in the United States:(40)
... cost overruns of 50 to 100 percent are common and ... overruns of more than 100
percent are not uncommon. Traffic forecasts that are off by 20 to 60 percent when
compared with actual development are frequent in large transportation projects.
Dr. Charles Lave, chair of the Economics Department at the University of California, Irvine has
suggested that the solution to forecasting inaccuracies would be to require consulting firms to
bond their forecasts.(41) Nothing short of such a solution would guarantee that the taxpayers will
not be forced to finance a financial bailout of the Florida high speed rail project.
| Based upon the findings of the National Research Council research, the Florida high speed rail project could require $15 billion to $31 billion in additional Florida taxpayer subsidies.(42) |
4.2: James Madison Institute Study
The JMI Evaluation projected that, under the most optimistic circumstances, the Florida high
speed rail line would carry 55 percent fewer riders than projected, and generate 45 percent less
revenue. Capital costs were projected at 15 percent higher than projections, while operating costs
were forecast at 29 percent higher than projection.
| Based upon the findings of the James Madison Institute research, the Florida high speed rail project could require $11 billion to $37 billion in additional Florida taxpayer subsidies.(43) |
5: Florida Taxpayer Tab: Another $11 Billion to $37 Billion
The two comprehensive tests produce similar results and suggest a range of additional taxpayer
obligation of $11 billion to $37 billion (Table: Comprehensive Test Comparisons)
|
Comprehensive Sensitivity Analysis Comparison: Additional Florida Taxpayer Subsidies | ||
| Comprehensive Test | Low | High |
| Application of National Research Council Findings | $15 Billion | $31 Billion |
| JMI Evaluation | $11 Billion | $37 Billion |
| In 1997$ | ||
There is nothing in the new ridership projections to suggest moderation of the previous JMI Evaluation projections. Once the bonds are issued, there will be no turning back. The taxpayers of the state of Florida will be required to provide the additional subsidies --- regardless of the cost --- because Florida's covenant to complete and operate will have, in effect, pledged the state's full faith and credit.
1. All financial amounts are in 1997$ unless otherwise indicated.
2. Wendell Cox, Evaluation of the FDOT-FOX Miami-Orlando-Tampa High-Speed Rail Proposal, James Madison Institute, April 1997.
3. Systra and KPMG Peat Marwick, Preliminary Summary Report: Florida High Speed Rail Project: Ridership Study, January 1998.
4. Systra and KPMG Peat Marwiick, Preliminary Summary Report: High Speed Rail Project: Ridership Study, January 1998, p. 1.
5. Systra, Florida Overland Express Ridership and Revenue Study: Draft Final Report, January 1998.
6. KPMG Peak Marwick LLP, Florida Overland Express High Speed Rail Study: Draft Ridership and Revenue Report, January 1998.
7. The 1995 FOX projected average passenger fare was $59.85 ($62.50 in 1997$). The 1997 projected average passenger fare is $51.83, 17 percent lower. Calculated from FOX, Systra and KPMG data.
8. All financial data in this report is in 1997 dollars (inflation adjustment has been performed).
9. FDOT and FOX are also seeking a $300 million grant from the federal government --- this would represent approximately five percent of project capital costs at current projections.
10. Calculated from original FOX/FDOT data.
11. US Department of Transportation Federal Railroad Administration, High-Speed Ground Transportation for America, September 1997.
12. This is the percentage of riders on high speed rail that would have been on airplanes if high speed rail were not available. In contrast, the new projections indicate that 58 percent of the airline passengers in the high speed rail corridor would switch to high speed rail.
13. Comparison of weighted average of high speed rail fares and air fares in the Central Florida to Southeast Florida and Tampa Bay to Southeast Florida markets. Calculated from data in Systra report and Domestic Airline Fares Consumer Report (US Department of Transportation, 1996: 3rd & 4th quarter, 1997: 1st & 2nd quarter).
14. The lower figure assumes air fares at their current level. The higher figure assumes air fares at their lowest level within the past two years.
15. Federal Railroad Administration.
16. This is the percentage of air passengers projected to switch to high speed rail. These passengers would comprise 30 percent of the high speed rail ridership.
17. Calculated from data in Systra report.
18. Cox, p. 26.
19. High Speed Rail Peer Review Board, Draft Preliminary Peer Review Report of Ridership and Revenue Forecasts for the Florida Overland Express, February 3, 1998.
20. FOX and FDOT have established a "peer group" of transportation and financial experts to review projections. In their report (High Speed Rail Peer Review Board, Draft Preliminary Peer Review Report of Ridership and Revenue Forecasts for the Florida Overland Express, February 3, 1998), the peer group referred to the projections on air connect passengers as "the most problematic aspect of the forecasts" and recommended that letters from airlines be submitted to document the assumptions. It should also be noted that peer group analysis does not necessarily reduce the uncertainty of projections and has been widely used in major infrastructure projects, including projects that fallen far short of their ridership projections.
21. The Systra report does not indicate the source of this estimate and JMI was unable to obtain sufficient documentation from FOX before this report's deadline.
22. Calculated from "The World Airline Report," Air Transport World, July 1997.
23. Perry Flint and Danna K. Henderson, "American at Bay," Air Transport World, March 1997.
24. Cox, p. 23.
25. A unit of FOX partner Bombardier is one of the world's leading suppliers of the new regional jets and other airliners designed for regional markets.
26. Airport capacity is being increased in Florida and additional airspace capacity is being created by improved computer flight technology. See Cox, p. 36-37.
27. Assumes load factors from the Systra report and a distribution of direct and air connect passengers equal to the overall ratio in the Central Florida - Southeast Florida market.
28. Systra report, page 5-20.
29. Projected FOX travel times have increased since the original FOX projections. For example, travel time from Orlando ro Miami has increased from 1:25 to 1:32.
30. U.S. Department of Transportation data indicates that the overwhelming majority of intercity trips of less than 100 miles are by automobile. Less than 0.5 percent of such trips are by airplane. Air travel tends to be slower than auto travel times because their "overhead" time --- traveling to the airport, checking in and waiting to depart. As a result, approximately 99 percent of travel in such short travel markets is by auto. High speed rail would face virtually the same competitive disadvantages (Source: calculated from Nationwide Personal Transportation Survey).
31. 1.8 million annual riders are anticipated in the short distance Tampa-Orlando and Miami-Palm Beach Markets. Using Nationwide Transportation Survey data, it is estimated that high speed rail demand in these corridors would be approximately 100,000 annually.
32. Based upon an estimate of train miles calculated from the original FOX proposal and the Systra report.
33. "Channel Tunnel: Prescott Vows to Ensure Link is Built," The Financial Times, February 25, 1998.
34. "Channel Tunnel" Last Gasp for Tunnel Rail Project," The Financial Times, January 30, 1998.
35. "Senior Railway Official Admits Folly of European Union Fail Policies," World Highways, January 1998 (quotation is from the article, which summarized Mr. Martinand's remarks).
36. Cox, p. 9.
37. There are a number of additional factors that render the French experience valueless in US projections, such as higher urban densities, more effective transit systems, higher automobile prices and lower incomes (purchasing power parity basis).
38. William Ahser quoted in Edward A. Mierzejewski, "Recognizing Uncertainly in the Transportation Planning Process: A Strategic Planning Approach," paper presented to the 76th Annual Meeting of the Transportation Research Board (Washington, DC, January 1997).
39. Cox, p. 14-17.
40. Mette K. Skamris and Bent Flyvbjerg, "Accuracy of Traffic Forecasts and Cost Estimates on Large Transportation Projects," Transportation Research Record (Washington, DC: Transportation Research Board, National Research Council), 1996.
41. Charles A. Lave, "Playing the Rail Forecasting Game," TR News 156, September-October 1991.
42. The lower estimate assumes costs at 50 percent higher and ridership 20 percent lower than projections. The higher estimate assumes costs at 100 percent higher and ridership at 60 percent lower than projected. If cost overruns were 200 percent --- less than Denver International Airport --- an additional $45 billion would be required from Florida taxpayers.
43. Cox, p. 32. Converted to 1997$.
